Building Tomorrow Today

 


We're building world-class facilities for the children and youth of our city!
 
The scope of this project includes the following areas:

Nursery (newborn – age 2)
Lobby Remodel

Pre-School Center (ages 3 – K5)
Auditorium, Playland, Craft Room, Classrooms

Elementary Center (1st Grade – 6th Grade)
Auditorium, Rangers, M-PACT, classrooms

Youth Center (Teenagers)
Worship Center, Café, Game Room, and classrooms
 
Commons Area (a ministry place for everyone)
Food Service, Coffee Shop, Bookstore, Grand Concourse
 
Campus Unification
Re-facing of 13th Street view
 
Schedule of Construction

Summer 2010
Site work (Utilities, Parking, Foundations, Demo)
 
Late Summer, Early Fall 2010
13th Street Façade, building superstructure
 
Fall, Early Winter 2010
Building Enclosure (Roofing, Aluminum and Glass)
 
Winter, Spring 2011
Interior Build out, major Mechanical, Electrical etc.
 
Spring, Early Summer 2011
Interior Finishes, Landscaping, Asphalt
 
Summer, Early Fall 2011
Occupancy new facility, Youth Remodel