The scope of this project includes the following areas:
Nursery (newborn – age 2)
Lobby Remodel
Pre-School Center (ages 3 – K5)
Auditorium, Playland, Craft Room, Classrooms
Elementary Center (1st Grade – 6th Grade)
Auditorium, Rangers, M-PACT, classrooms
Youth Center (Teenagers)
Worship Center, Café, Game Room, and classrooms
Lobby Remodel
Pre-School Center (ages 3 – K5)
Auditorium, Playland, Craft Room, Classrooms
Elementary Center (1st Grade – 6th Grade)
Auditorium, Rangers, M-PACT, classrooms
Youth Center (Teenagers)
Worship Center, Café, Game Room, and classrooms
Commons Area (a ministry place for everyone)
Food Service, Coffee Shop, Bookstore, Grand Concourse
Food Service, Coffee Shop, Bookstore, Grand Concourse
Campus Unification
Re-facing of 13th Street view
Re-facing of 13th Street view
Schedule of Construction
Summer 2010
Site work (Utilities, Parking, Foundations, Demo)
Site work (Utilities, Parking, Foundations, Demo)
Late Summer, Early Fall 2010
13th Street Façade, building superstructure
13th Street Façade, building superstructure
Fall, Early Winter 2010
Building Enclosure (Roofing, Aluminum and Glass)
Building Enclosure (Roofing, Aluminum and Glass)
Winter, Spring 2011
Interior Build out, major Mechanical, Electrical etc.
Interior Build out, major Mechanical, Electrical etc.
Spring, Early Summer 2011
Interior Finishes, Landscaping, Asphalt
Interior Finishes, Landscaping, Asphalt
Summer, Early Fall 2011
Occupancy new facility, Youth Remodel
Occupancy new facility, Youth Remodel